Skip to content

How do I write a good request for a plumbing plan?

Name the fixtures you want served and where the water comes from. Here's a request that does both:

"Run hot and cold water from the water heater in the Utility room to the kitchen sink, both lavatories and the shower, and run sanitary drainage from those fixtures to the existing stack, sized to the plumbing code."

Name the source: a water heater, riser or stack already on the plan. If you don't name one and the plan has none, the water supply starts at the nearest exterior wall to the first fixture.

Let it size the pipe, or give the size: water supply is sized from the fixtures on each run using the plumbing code your project lists, and drainage by fixture units and slope. If you state a size, it draws that size. The finished job names the table each size came from.

Vent and gas: ask for them the same way, for example "run a gas line from the meter to the range and the furnace". Every run is routed around walls and through door openings, and hot, cold and drainage each go on their own layer.

Inverts and slopes: give AutoMEP the invert levels or the slope and it writes them on the drain run. It doesn't work them out from a flat plan.

Fixtures and drains: ask for new fixtures by room, for example "a floor drain in each restroom". Floor drains go in the middle of the room, and AutoMEP uses your drawing's own fixture blocks when it has them.

Schedules and risers: ask for a fixture schedule beside the plan, or see riser diagrams for a riser.

One request or several: on a trial or the Starter plan, each request starts again from your original upload, so put supply and drainage in one request. On Pro and Team, with Build on the last result ticked, each request adds to the one before.

More in MEP Operations

Did this answer your question? If not, contact support and send us the drawing.